Others · 1 building · 9 unitsRERA P51800055091

Rishab Laxmi

Deedo IDDP-MSB-DKX5

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 67% of its units are booked.

Malad, Mumbai Suburban 400064 · Promoter: Aditi Developers

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales67% booked6 of 9 units · as the promoter reported to MahaRERA
Rishab Laxmi project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 29 Feb 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51800055091
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180005509129 Feb 202431 Dec 202630 Apr 2027Aditi DevelopersProject page
Documents69

1 document held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card Aditi devlopers .pdf · uploaded 6 Jan 2024Source

Legal

  • Declaration Form BForm B (16).pdf · uploaded 6 Jan 2024Source
  • Legal Title reportLegal Title Report SJ Mishra.pdf · uploaded 11 Jan 2024Source

Migrated

  • 1 PAN CardPan Card Aditi devlopers .pdf · uploaded 6 Jan 2024Source
  • 1 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE SELF DECLARATION (3).pdf · uploaded 6 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCE SELF DECLARATION (3).pdf · uploaded 6 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)IOD Drawing Plan_1-3.pdf · uploaded 6 Jan 2024Source
Show all 69 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)IOD Drawing Plan_4-end.pdf · uploaded 6 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentIOD Approval Letter.pdf · uploaded 6 Jan 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentPlinth FirstCC_signed.pdf · uploaded 6 Jan 2024Source
  • 1 Declaration about Commencement CertificateCC COVERING LETTER (3).pdf · uploaded 6 Jan 2024Source
  • 1 Declaration in FORM BForm B (16).pdf · uploaded 6 Jan 2024Source
  • 1 CERSAI detailsCERSAI DECLARATION (11).pdf · uploaded 6 Jan 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER FINAL (2).pdf · uploaded 6 Jan 2024Source
  • 1 Copy of the legal title reportLegal Title Report SJ Mishra.pdf · uploaded 11 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsoutput (20).pdf · uploaded 11 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Details.pdf · uploaded 11 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation report (1).pdf · uploaded 12 Jan 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation report for agreement for sale_0001 (1).pdf · uploaded 12 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 13 Jan 2024Source
  • 1 Proforma of Agreement for saleagreement rishab laxmi.pdf · uploaded 14 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 03 24.pdf · uploaded 26 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 06 24.pdf · uploaded 26 Dec 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 09 24.pdf · uploaded 26 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 03 24.pdf · uploaded 26 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 06 24.pdf · uploaded 26 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 09 24.pdf · uploaded 26 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 03 24.pdf · uploaded 26 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 06 24.pdf · uploaded 26 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 09 24.pdf · uploaded 26 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A 23-24.pdf · uploaded 26 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 23-24.pdf · uploaded 26 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 17 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 17 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 17 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 11 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 11 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 11 Apr 2025Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 30 Oct 2025Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 30 Oct 2025Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 30 Oct 2025Source
  • Withdrawal Update Form 1Mr Sumit Shah Partner of Ms Aditi Developers Rishab Laxmi.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 2FORM 2 RISHAB LAXMI.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 3CA Certificate Form 3 Rishab Laxmi.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 1Completion of Construction Work Certificate of Rishab Aangan.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2FORM 2 RISHAB LAXMI 31 03 2026.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3CA Certificate Laxmi.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1CONSULTING ARCHITECT CERTIFICATE Rishab Laxmi.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 RISHAB LAXMI 30 06 2026.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Rishab Laxmi.pdf · uploaded 14 Jul 2026Source
  • Form 2A (FY 2025-2026)form 2A_RISHAB LAXMI_.pdf · uploaded 6 Oct 2026Source
  • Form 5 (FY 2025-2026)Form 5 Rishab Laxmi.pdf · uploaded 6 Oct 2026Source

Technical

  • DocumentIOD Drawing Plan_1-3.pdf · uploaded 6 Jan 2024Source
  • DocumentIOD Drawing Plan_4-end.pdf · uploaded 6 Jan 2024Source
  • DocumentIOD Approval Letter.pdf · uploaded 6 Jan 2024Source
  • Document14618843-15-05-2025 07-54-34$_$DRAWING (1).pdf · uploaded 6 Aug 2025Source
  • Document2478611_FurtherCC_signed.pdf · uploaded 6 Aug 2025Source
  • Document2463181Amendletter_signed (1).pdf · uploaded 6 Aug 2025Source

Technical (Architect)

  • Documentform 1 03 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 1 06 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 1 09 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 1.pdf · uploaded 11 Apr 2025Source
  • DocumentCONSULTING ARCHITECT CERTIFICATE Rishab Laxmi.pdf · uploaded 14 Jul 2026Source

Technical (Engineer)

  • Documentform 2 03 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 2 06 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 2 09 24.pdf · uploaded 26 Dec 2024Source
  • Documentform 2.pdf · uploaded 11 Apr 2025Source
  • DocumentFORM 2 RISHAB LAXMI 30 06 2026.pdf · uploaded 14 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals121

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—33 units in all
Address
121, Off The Junction Of Mamletdarwadi Main Road And Of Mamletdarwadi Road No. 2, Malad WestPIN 400064
Village
Malad, Borivali taluka
Designated bank account
159
Developed in phases
No

Survey, CTS, gat or plot numbers

121

Boundaries

North
By The Mamlatdar Wadi Main Road
South
By Plot No 3 Of The Private Scheme
East
By The Mamlatdar Wadi 2nd Cross Lane
West
By Plot No 1 Of The Private Scheme

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking33 units

33 units registered

— · 33 units
TypeCarpet areaUnits
——33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSomaiya and Associates—
Chartered accountantDhawal Vora & Associates—
EngineerMr Abhijit V Phatarpekar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology