Deedo IDDP-MSB-DH5WCompletion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 7% of its units are booked.
Chembur, Mumbai Suburban 400071 · by Majestic Royale Developers · 75% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Oct 2028
- This projectRegistered 12 Mar 2025, completion promised 30 Jun 2028, revised to 30 Oct 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51800079559
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800079559 | 12 Mar 2025 | 30 Jun 2028 | 30 Oct 2028 | Majestic Royale Developers | Project page |
Documents58
1 document held by Deedo, 57 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card (Majestic Royale Developers).pdf · uploaded 31 Dec 2024Source
Legal
Migrated
- 1 PAN CardPan Card (Majestic Royale Developers).pdf · uploaded 31 Dec 2024Source
- 1 Copy of the legal title reportTitle Report Narulla (1).pdf · uploaded 31 Dec 2024Source
- 2 a Details of encumbrances concerned to FinanceNo Encumberance_.pdf · uploaded 31 Dec 2024Source
- 1 Proforma of Allotment letterProforma Allotement Letter Narulla.pdf · uploaded 31 Dec 2024Source
Show all 58 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BGetUserDocumentFileContent (2).pdf · uploaded 31 Dec 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentNarulla First CC.pdf · uploaded 31 Dec 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 31 Dec 2024Source
- 1 CERSAI detailsCERSAI DECLARATION (18).pdf · uploaded 31 Dec 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A - New Bank Letter.pdf · uploaded 31 Dec 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Allottment_.pdf · uploaded 31 Dec 2024Source
- 2 b Details of encumbrances concerned to LegalNo Encumberance_.pdf · uploaded 31 Dec 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Agreement_.pdf · uploaded 31 Dec 2024Source
- 1 Proforma of Agreement for saleAFS QUERY.pdf · uploaded 31 Dec 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A_merged.pdf · uploaded 31 Dec 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Narulla.pdf · uploaded 31 Dec 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for secured unsecured (1).pdf · uploaded 31 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form 1 Narulla_.pdf · uploaded 1 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed CA Certificate_Narula Building CHSL_Reg_.pdf · uploaded 2 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Narulla (1)_compressed.pdf · uploaded 2 Jan 2025Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 2 Jan 2025Source
- 1 Other – TechnicalAnnexure A_.pdf · uploaded 2 Jan 2025Source
- 1 Copy of Layout Approval (in case of layout)Narulla Approved Drawing.pdf · uploaded 3 Jan 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentIssue Letter FOR CORRIGENDUM.pdf · uploaded 11 Feb 2025Source
- 1 a Details of encumbrances concerned to Finance6-3-25 No encumbrance self declaration_.pdf · uploaded 12 Feb 2025Source
- 1 b Details of encumbrances concerned to Legal6-3-25 No encumbrance self declaration_.pdf · uploaded 12 Feb 2025Source
- 2 Other – TechnicalForm B Promoter (2).pdf · uploaded 22 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 March 2025_.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2025.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2025 (1).pdf · uploaded 17 Apr 2025Source
- Withdrawal Update Form 1Form 1 Narulla Sep 2025.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 2Form 2 Narulla Sep 2025_11zon.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 3Form 3 Sep 2025 revised final sept 25.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 1Form 1 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 1Form 1 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 2Form 2 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 2Form 2 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 3Form 3 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 3Form 3 Dec 2025.pdf · uploaded 17 Mar 2026Source
- Withdrawal Update Form 1Form 1 March 2026.pdf · uploaded 22 May 2026Source
- Withdrawal Update Form 2Form 2 March 2026_.pdf · uploaded 22 May 2026Source
- Withdrawal Update Form 3Form 3 Dec 2025.pdf · uploaded 22 May 2026Source
- Withdrawal Update Form 1form 1.pdf · uploaded 30 Jul 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 30 Jul 2026Source
- Withdrawal Update Form 3form 3.pdf · uploaded 30 Jul 2026Source
Technical
- DocumentIOD.pdf · uploaded 31 Dec 2024Source
- Other – TechnicalAnnexure A_.pdf · uploaded 2 Jan 2025Source
- DocumentNarulla Approved Drawing.pdf · uploaded 3 Jan 2025Source
- DocumentIssue Letter FOR CORRIGENDUM.pdf · uploaded 11 Feb 2025Source
- Other – TechnicalForm B Promoter (2).pdf · uploaded 22 Feb 2025Source
- DocumentFull Drawing.pdf · uploaded 21 Jan 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 852/1 to 6, 852 part
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, tenant flat14 units in all
- Address
- 852 part &852/1 to 6, EXISTING ROAD NO 2, CHEMBURPIN 400071
- Village
- Chembur, Kurla taluka
- Location
- 19.06060, 72.90151
- Land area for this project
- 878 sq m (9,446 sq ft)
- Permissible built-up area
- 2,646 sq m (28,479 sq ft)
- Sanctioned built-up area
- 2,646 sq m (28,479 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
852 part &852/1 to 6
Boundaries
- North
- Vishranti Chsl
- South
- existing road no 21
- East
- existing Road no 2
- West
- Revati CHSL
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking14 units
1 of 14 units booked (7%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 60.91 sq m · 656 sq ft | 1 | 0 |
| 2BHK | 65.38 sq m · 704 sq ft | 1 | 1 |
| 3BHK | 96.77 sq m · 1,042 sq ft | 2 | 0 |
| tenant flat | 39.17 sq m · 422 sq ft | 1 | 0 |
| tenant flat | 43.11 sq m · 464 sq ft | 3 | 0 |
| tenant flat | 58.07 sq m · 625 sq ft | 1 | 0 |
| tenant flat | 58.27 sq m · 627 sq ft | 1 | 0 |
| tenant flat | 60.91 sq m · 656 sq ft | 1 | 0 |
Show all 11 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| tenant flat | 70.74 sq m · 761 sq ft | 1 | 0 |
| tenant flat | 93.1 sq m · 1,002 sq ft | 1 | 0 |
| tenant flat | 96.77 sq m · 1,042 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Aditi Dilip Yadav | — |
| Chartered accountant | Nehali Doshi Doshi | — |
| Engineer | Vinayak Chopdekar And Associates | — |
Source: MahaRERA project page. Contact details are not shown.