Skip to content
Mixed · 1 building · 38 unitsRERA P51900034425

Kings Tower

Deedo IDDP-MUM-3EVE

Completion was pushed back 4 months, to Jan 2027; no MahaRERA orders on record; 0% of its units are booked.

Ward E, Maharashtra 400008 · by Mohammed Eshaq Ali Vadgama

DeliveryExtended 4 moPromised Sep 2026 · now due Jan 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 38 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jan 2027

  • This projectRegistered 5 Apr 2022, completion promised 29 Sep 2026, revised to 29 Jan 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51900034425
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P519000344255 Apr 202229 Sep 202629 Jan 2027Mohammed Eshaq Ali VadgamaProject page
Documents71

1 document held by Deedo, 70 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card Mohd Eshaq.pdf · uploaded 9 Mar 2022Source

Legal

  • Legal Title reportRera Final Title Report Format - A_compressed.pdf · uploaded 9 Mar 2022Source
  • Declaration Form BRera Affidavit Cum Declaration.pdf · uploaded 9 Mar 2022Source

Migrated

  • 1 PAN CardPan card Mohd Eshaq.pdf · uploaded 9 Mar 2022Source
  • 1 Copy of the legal title reportRera Final Title Report Format - A_compressed.pdf · uploaded 9 Mar 2022Source
  • 1 Details of encumbrancesMYSCAN_20220328_0007.pdf · uploaded 9 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentPLINTH CC ZERO FSI.pdf · uploaded 9 Mar 2022Source
Show all 71 documentsShow fewer documents

Migrated

  • 1 Declaration about Commencement CertificateRera Declaration For CC.pdf · uploaded 9 Mar 2022Source
  • 1 Declaration in FORM BRera Affidavit Cum Declaration.pdf · uploaded 9 Mar 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200233167521_For_Asset_Based_Search_23_03_2022_13_26_29_999.pdf · uploaded 9 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 sign copy_compressed.pdf · uploaded 9 Mar 2022Source
  • 1 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 9 Mar 2022Source
  • 2 Proforma of Allotment letterRera Allotment Letter_compressed.pdf · uploaded 9 Mar 2022Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20220328_0007.pdf · uploaded 31 Mar 2022Source
  • 2 Copy of Layout Approval (in case of layout)MYSCAN_20220330_0006_compressed.pdf · uploaded 31 Mar 2022Source
  • 3 Copy of Layout Approval (in case of layout)MYSCAN_20220330_0005_compressed.pdf · uploaded 31 Mar 2022Source
  • 4 Copy of Layout Approval (in case of layout)MYSCAN_20220330_0004_compressed.pdf · uploaded 31 Mar 2022Source
  • 5 Copy of Layout Approval (in case of layout)MYSCAN_20220330_0008_compressed.pdf · uploaded 31 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted development2293980_IOD_signed (1).pdf · uploaded 31 Mar 2022Source
  • Form 1SUTTARWALA RERA 2023.pdf · uploaded 29 Aug 2025Source
  • Form 21 Form 2 Mar 23.pdf · uploaded 29 Aug 2025Source
  • Form 31 Form 3 Mar 23.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory1 Mar 23.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Mar 23.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA 2024.pdf · uploaded 29 Aug 2025Source
  • Form 22 Form 2 Mar 24.pdf · uploaded 29 Aug 2025Source
  • Form 32 Form 3 Mar 24.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory2 Mar 24.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Mar 24.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA 2025.pdf · uploaded 29 Aug 2025Source
  • Form 23 Form 2 Jun 24.pdf · uploaded 29 Aug 2025Source
  • Form 33 Form 3 Jun 24.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory3 Jun 24.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Jun 24.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA 2025.pdf · uploaded 29 Aug 2025Source
  • Form 24 Form 2 Sep 24.pdf · uploaded 29 Aug 2025Source
  • Form 34 Form 3 Sep 24.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory4 Sep 24.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Sep 24.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA 2025.pdf · uploaded 29 Aug 2025Source
  • Form 25 Form 2 Dec 24.pdf · uploaded 29 Aug 2025Source
  • Form 35 Form 3 Dec 24.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory5 Dec 24.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Dec 24.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA 2025.pdf · uploaded 29 Aug 2025Source
  • Form 26 Form 2 Mar 25.pdf · uploaded 29 Aug 2025Source
  • Form 36 Form 3 Mar 25.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory6 Mar 25.pdf · uploaded 29 Aug 2025Source
  • Form 1SUTTARWALA RERA Jun 25.pdf · uploaded 29 Aug 2025Source
  • Form 27 Form 2 Jun 25.pdf · uploaded 29 Aug 2025Source
  • Form 37 Form 3 Jun 25.pdf · uploaded 29 Aug 2025Source
  • Disclosure of Sold and Booked Inventory7 Jun 25.pdf · uploaded 29 Aug 2025Source
  • Self-declaration of Quarterly ProgressQPR Jun 25.pdf · uploaded 29 Aug 2025Source
  • Withdrawal Update Form 1Form - 1_Sep 25 - King Tower.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 2Form - 2_Sep 25 - King Tower.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 3Form III (Sep 25) - King Tower_compressed.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Dec 25 - King Circle.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Dec 25 - King Circle.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 3RERA form lll dec25.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Mar 26 - King Circle.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Mar 26 - King Circle.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 3Scan Form III Mar 26-Kings Tower.pdf · uploaded 3 Jun 2026Source

Technical

  • DocumentMYSCAN_20220328_0007.pdf · uploaded 31 Mar 2022Source
  • DocumentMYSCAN_20220330_0006_compressed.pdf · uploaded 31 Mar 2022Source
  • DocumentMYSCAN_20220330_0005_compressed.pdf · uploaded 31 Mar 2022Source
  • DocumentMYSCAN_20220330_0004_compressed.pdf · uploaded 31 Mar 2022Source
  • DocumentMYSCAN_20220330_0008_compressed.pdf · uploaded 31 Mar 2022Source
  • Document2293980_IOD_signed (1).pdf · uploaded 31 Mar 2022Source

Technical (Architect)

  • DocumentForm 1 Mar 26 - King Circle.pdf · uploaded 2 Jun 2026Source

Technical (Engineer)

  • DocumentForm 2 Mar 26 - King Circle.pdf · uploaded 2 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1665 1/1665 at Ward E

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK38 units in all
Address
1665 1/1665, Morland Road, Mumbai CentralPIN 400008
Land area for this project
1,782 sq m (19,186 sq ft)
Permissible built-up area
6,882 sq m (74,077 sq ft)
Sanctioned built-up area
6,882 sq m (74,077 sq ft)
Recreational open space
217 sq m (2,341 sq ft)
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

1665 1/1665 at Ward E

Land as published on MahaRERA's project page

1665 1/1665

Boundaries

North
Mehfil Hall
South
Sharaf Building
East
Ismail Palace
West
Morland Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking38 units

0 of 38 units booked (0%), as the promoter reported to MahaRERA

1BHK · 24 units2BHK · 3 units3BHK · 11 units
TypeCarpet areaUnitsBooked
1BHK40.88 sq m · 440 sq ft240
2BHK66.89 sq m · 720 sq ft30
3BHK82.5 sq m · 888 sq ft110

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGajjar & Associates—
Chartered accountantJ N Mehta & Associates—
EngineerSupcons Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology