Silver Springs
Completion was pushed back 5 years and 10 months to Dec 2024, and that date has passed too; no MahaRERA orders on record; 62% of its units are booked.
Kolhapur (M Corp.), Kolhapur 416012 · Promoter: Mahalaxmi Developers
Completion was pushed back 5 years and 10 months to Dec 2024, and that date has passed too
- This projectRegistered 19 Aug 2017, completion promised 28 Feb 2019, revised to 31 Dec 2024, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP53000009173
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P53000009173 | 19 Aug 2017 | 28 Feb 2019 | 31 Dec 2024 | Mahalaxmi Developers | Project page |
Documents43
2 documents held by Deedo, 41 filings listed on MahaRERA's project page
Finance
- PAN Card1 Pan card Mahalaxmi Developers.pdf · uploaded 8 Aug 2017Source
Legal
Show all 43 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)4a Layout.pdf · uploaded 8 Aug 2017Source
- 2 Copy of Layout Approval (in case of layout)4b Layout.pdf · uploaded 8 Aug 2017Source
- 1 Building Plan Approval (IOD)12 Silver spring order.pdf · uploaded 8 Aug 2017Source
- 1 Declaration in FORM B6 B Form.pdf · uploaded 8 Aug 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)7 Silver spring form 1.pdf · uploaded 8 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11 Silver spring Form 2.pdf · uploaded 8 Aug 2017Source
- 1 Certificates of CA (Form 3)9 Silver_Spring Form 3.pdf · uploaded 8 Aug 2017Source
- 1 Proforma of Allotment letter5a Silver Springs Allotment Letter.pdf · uploaded 8 Aug 2017Source
- 2 Proforma of Allotment letterSilver spring Agreement (2).pdf · uploaded 8 Aug 2017Source
- 1 Architect’s Certificate on Completion of Project (Form 4)form4.pdf · uploaded 21 Jan 2020Source
- 3 Copy of Layout Approval (in case of layout)Silver spring 1 of 3.pdf · uploaded 19 Aug 2021Source
- 4 Copy of Layout Approval (in case of layout)Silver spring 2 of 3.pdf · uploaded 19 Aug 2021Source
- 5 Copy of Layout Approval (in case of layout)Silver spring 3 of 3.pdf · uploaded 19 Aug 2021Source
- 1 Declaration about Commencement CertificateCommencement.pdf · uploaded 19 Aug 2021Source
- 2 Declaration about Commencement CertificateCommencement1.pdf · uploaded 19 Aug 2021Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 19 Aug 2021Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2a 20.pdf · uploaded 19 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2a 21.pdf · uploaded 19 Aug 2021Source
- 1 Disclosure of sold/ booked inventorySold Unsold Unit.pdf · uploaded 24 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentPERMISSION.pdf · uploaded 26 Aug 2021Source
- 2 Certificates of CA (Form 3)fORM 3.pdf · uploaded 26 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)17-18.pdf · uploaded 26 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)18-19.pdf · uploaded 26 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)19-20.pdf · uploaded 26 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)20-21.pdf · uploaded 26 Aug 2021Source
- 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 2 Sep 2021Source
Technical
- Document4a Layout.pdf · uploaded 8 Aug 2017Source
- Document12 Silver spring order.pdf · uploaded 8 Aug 2017Source
- Document4b Layout.pdf · uploaded 8 Aug 2017Source
- DocumentSilver spring 1 of 3.pdf · uploaded 19 Aug 2021Source
- DocumentSilver spring 2 of 3.pdf · uploaded 19 Aug 2021Source
- DocumentSilver spring 3 of 3.pdf · uploaded 19 Aug 2021Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 19 Aug 2021Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 19 Aug 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsS No 904/1 plot No 4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK13 units in all
- Address
- S No 904/1 plot No 4PIN 416012
- Village
- Kolhapur (M Corp.), Karvir taluka
- Location
- 16.71319, 74.22927
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 904 1 5
- South
- S No 904 2 3A
- East
- S No 904 1 3
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking13 units
8 of 13 units booked (62%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.25 sq m · 455 sq ft | 3 | 3 |
| 2BHK | 75 sq m · 807 sq ft | 10 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sandeep S Nerlekar | — |
| Engineer | Mahesh Kumbhojkar | — |
Source: MahaRERA project page. Contact details are not shown.