Sarlashkar Heights
Deedo IDDP-KOL-55Q1Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 31% of its units are booked.
Karvir, Maharashtra 416003 · Promoter: Vst Unity Developers Pvt. Ltd.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 10 Jan 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Sarlashkar Heights Apartment14 floors · 55 units33% booked
- Sarlashkar Niwas Bungalow 11 floor · 1 unit0% booked
- Sarlashkar Niwas Bungalow 21 floor · 1 unit0% booked
- Sarlashkar Niwas Bungalow 31 floor · 1 unit0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP53000048650
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P53000048650 | 10 Jan 2023 | 31 Dec 2027 | 30 Apr 2028 | Vst Unity Developers Pvt. Ltd. | Project page |
Documents108
1 document held by Deedo, 107 filings listed on MahaRERA's project page
Finance
- PAN Card1 Vst pan.pdf · uploaded 15 Dec 2022Source
Legal
Show all 108 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)5 LAYOUT.pdf · uploaded 15 Dec 2022Source
- 1 Building Plan Approval / NA Order for plotted development6 Plan 1.pdf · uploaded 15 Dec 2022Source
- 2 Building Plan Approval / NA Order for plotted development6 Plan 2.pdf · uploaded 15 Dec 2022Source
- 3 Building Plan Approval / NA Order for plotted development6 Plan 3.pdf · uploaded 15 Dec 2022Source
- 4 Building Plan Approval / NA Order for plotted development6 Plan 4.pdf · uploaded 15 Dec 2022Source
- 1 Commencement Certificates / NA Order for plotted development7 Commencement Certificate Vst.pdf · uploaded 15 Dec 2022Source
- 1 Declaration about Commencement Certificate8 DECLARATION ABOUT CC.pdf · uploaded 15 Dec 2022Source
- 1 Declaration in FORM B9 FORM N PROMOTER.pdf · uploaded 15 Dec 2022Source
- 2 Declaration in FORM B9 FORM B LANDOWNER.pdf · uploaded 15 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)11 FORM 1.pdf · uploaded 15 Dec 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 FORM 2.pdf · uploaded 15 Dec 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_.pdf · uploaded 15 Dec 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 form upload.pdf · uploaded 15 Dec 2022Source
- 1 Proforma of Allotment letter16 ALLOTMENT LETTER.pdf · uploaded 15 Dec 2022Source
- 1 Proforma of Agreement for sale17 AGREEMENT TO SELL.pdf · uploaded 15 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same36 BANK LETTER.pdf · uploaded 15 Dec 2022Source
- 1 Deviation Report with respect to Allotment letter37 NO DEVIATION ALLOTMENT LETTER.pdf · uploaded 15 Dec 2022Source
- 1 Deviation Report with respect to model copy of Agreement35 NO DEVIATION AGREEMENT TO SELL.pdf · uploaded 15 Dec 2022Source
- 1 Copy of the legal title reportVST FINAL TITLE UPLOAD.pdf · uploaded 30 Dec 2022Source
- 2 a Details of encumbrances concerned to Finance3 fINANCE lETTER.pdf · uploaded 30 Dec 2022Source
- 2 b Details of encumbrances concerned to Legal3 fINANCE lETTER.pdf · uploaded 30 Dec 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 20 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 20 Sep 2023Source
- 1 Disclosure of sold/ booked inventorySold Booked Inventory.pdf · uploaded 20 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 20 Sep 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)archi june upload.pdf · uploaded 21 Sep 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer june upload.pdf · uploaded 21 Sep 2023Source
- 2 Disclosure of sold/ booked inventorySold Booked Inventory.pdf · uploaded 21 Sep 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA june upload.pdf · uploaded 21 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - 2022-23 VST.pdf · uploaded 7 Oct 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE 3-10-23.pdf · uploaded 10 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer's certificate 9-10-23.pdf · uploaded 10 Oct 2023Source
- 3 Disclosure of sold/ booked inventorysold Booked inventory 10-10-23.pdf · uploaded 10 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 8-10-23.pdf · uploaded 10 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A Quality Assurance certificate 31 March 2023.pdf · uploaded 11 Oct 2023Source
- 3 a Details of encumbrances concerned to Financeencumbrances Declaration Finance.pdf · uploaded 15 Jan 2024Source
- 3 b Details of encumbrances concerned to Legalencumbrances Declaration Finance.pdf · uploaded 15 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 15 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jan 2024Source
- 4 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 15 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 15 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Jan 2024Source
- 4 a Details of encumbrances concerned to FinanceMortgage Deed Index II.pdf · uploaded 17 Jan 2024Source
- 4 b Details of encumbrances concerned to LegalMortgage Deed Index II.pdf · uploaded 17 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 18 April 2024.pdf · uploaded 19 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate 18 April 2024.pdf · uploaded 19 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A 18 April 2024.pdf · uploaded 19 Apr 2024Source
- 5 Disclosure of sold/ booked inventorySold Unsold Inventory 18 April 2024.pdf · uploaded 19 Apr 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 18 April 2024.pdf · uploaded 19 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2 A 18 April 2024.pdf · uploaded 8 May 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate for rera update July 24.pdf · uploaded 12 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Enginner Certificate July 24 (1).pdf · uploaded 12 Jul 2024Source
- 6 Disclosure of sold/ booked inventorySold Unsold final 10 July 24.pdf · uploaded 12 Jul 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 10 July 24 .pdf · uploaded 12 Jul 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 10 July 24 _compressed (1).pdf · uploaded 12 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed (5).pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_compressed (26).pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySold unsold inventory.pdf · uploaded 19 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 VST .pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed (9).pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed (45).pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate Form 1.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 CA Certificate_compressed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 2.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 19 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality assurance certificate Form 2A.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 16 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 16 Jul 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 16 Jul 2025Source
- Form 5 (FY 2024-2025)Cosolidate Form_5 VST.pdf · uploaded 10 Oct 2025Source
- Withdrawal Update Form 1Architect certificate.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2Engg Certificate.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3 CA certificate.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1Rera Update Architects Certificate_compressed.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Rera Update Engineer Certificate.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form - 3 CA Certificate (1)_11zon.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Architect Certificate.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Engineer Certificate.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3CA Certificate.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Architects Certificate_compressed.pdf · uploaded 11 Jul 2026Source
- Withdrawal Update Form 2Engineers Certificate_11zon.pdf · uploaded 11 Jul 2026Source
- Withdrawal Update Form 3CA Certificate_11zon.pdf · uploaded 11 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsC. S. No. 27/C/36/C/A, C.S. No. 27/C/36/C/B at Karvir
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Bungalow58 units in all
- Address
- C. S. No. 27/C/36/C/A and C.S. No. 27/C/36/C/B, Sarlashkar Park, Tarabai ParkPIN 416003
- Village
- Kolhapur (M Corp.), Karvir taluka
- Location
- 16.71801, 74.24523
- Designated bank account
- 164
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- 7 and half Mtr Wide Road and C S No 27C 36A
- South
- C S No 27C 36B
- East
- 18 Mtr Wide Road
- West
- Shiv Shakti Apartment
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking58 units
18 of 58 units booked (31%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Sarlashkar Heights Apartment | 2BHK | 75.72 sq m · 815 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 2BHK | 75.84 sq m · 816 sq ft | 10 | 6 |
| Sarlashkar Heights Apartment | 2BHK | 75.94 sq m · 817 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 2BHK | 75.96 sq m · 818 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 2BHK | 78.19 sq m · 842 sq ft | 1 | 1 |
| Sarlashkar Heights Apartment | 2BHK | 78.55 sq m · 846 sq ft | 11 | 0 |
| Sarlashkar Heights Apartment | 2BHK | 78.69 sq m · 847 sq ft | 2 | 1 |
| Sarlashkar Heights Apartment | 3BHK | 102.38 sq m · 1,102 sq ft | 3 | 1 |
Show all 27 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Sarlashkar Heights Apartment | 3BHK | 102.58 sq m · 1,104 sq ft | 2 | 2 |
| Sarlashkar Heights Apartment | 3BHK | 102.68 sq m · 1,105 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 102.74 sq m · 1,106 sq ft | 3 | 2 |
| Sarlashkar Heights Apartment | 3BHK | 102.75 sq m · 1,106 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 102.8 sq m · 1,107 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 102.83 sq m · 1,107 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 102.94 sq m · 1,108 sq ft | 2 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 103.53 sq m · 1,114 sq ft | 4 | 2 |
| Sarlashkar Heights Apartment | 3BHK | 103.73 sq m · 1,117 sq ft | 1 | 1 |
| Sarlashkar Heights Apartment | 3BHK | 103.79 sq m · 1,117 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 103.84 sq m · 1,118 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 103.89 sq m · 1,118 sq ft | 2 | 1 |
| Sarlashkar Heights Apartment | 3BHK | 103.91 sq m · 1,118 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 103.96 sq m · 1,119 sq ft | 1 | 0 |
| Sarlashkar Heights Apartment | 3BHK | 103.98 sq m · 1,119 sq ft | 1 | 1 |
| Sarlashkar Heights Apartment | 3BHK | 104.1 sq m · 1,121 sq ft | 2 | 0 |
| Sarlashkar Niwas Bungalow 1 | Bungalow | 354.22 sq m · 3,813 sq ft | 1 | 0 |
| Sarlashkar Niwas Bungalow 2 | Bungalow | 354.22 sq m · 3,813 sq ft | 1 | 0 |
| Sarlashkar Niwas Bungalow 3 | Bungalow | 354.22 sq m · 3,813 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vision Associates | — |
| Chartered accountant | Amit Madanrao Shinde | — |
| Chartered accountant | Shankar Patil & Asscoiates | — |
| Engineer | Mahesh V Patole | — |
Source: MahaRERA project page. Contact details are not shown.