Shri Apartment
LapsedBhusawal (Ct), Jalgaon 425201 |Promoter: Milan Devanand Prajapati
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Lapsed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, Shop22 units in all
- Land area for this project
- 282 sq m (3,035 sq ft)
- Permissible built-up area
- 554 sq m (5,963 sq ft)
- Sanctioned built-up area
- 554 sq m (5,963 sq ft)
- Address
- Cts No 200/9, 10, 11, 12, 13, 30, 31, 32, 33, 34, Bhusawal, BhusawalPIN 425201
- Designated bank account
- The Cosmos Co Operative Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Sep 2023
The latest completion date on record passed 3 years and 1 month ago.
- Registered
- 4 Jul 2020
- Promised
- 30 Sep 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P49900025722 | 4 Jul 2020 | 30 Sep 2023 | — | Milan Devanand Prajapati | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Shri Apartment | 5 | 22 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
22 units registered
| Type | Carpet area | Units |
|---|---|---|
| 1BHK | 85 sq m · 915 sq ft | 3 |
| 2BHK | 340 sq m · 3,660 sq ft | 9 |
| Shop | 128 sq m · 1,378 sq ft | 10 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Shri Apartment
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
11 documents held by Deedo, 20 filings listed on MahaRERA's project page
Commencement certificates
Document library
- Details of encumbrances2 ENCUMBRANCE CERTIFICATES.pdf · uploaded 30 Jun 2020View
- Building Plan Approval / NA Order for plotted development4 BUILDING PLAN APPROVAL.pdf · uploaded 30 Jun 2020View
- Commencement Certificates / NA Order for plotted development5 COMMENCEMENT CERTIFICATE.pdf · uploaded 30 Jun 2020View
- Declaration in FORM B6 FORM B.PDF · uploaded 30 Jun 2020View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)7 FORM 1.PDF · uploaded 30 Jun 2020View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)8 FROM 2.PDF · uploaded 30 Jun 2020View
- Proforma of Allotment letter10 PERFOMA AGREEMENT.pdf · uploaded 30 Jun 2020Source
- Copy of Layout Approval (in case of layout)3 LAYOUT PLAN.pdf · uploaded 30 Jun 2020View
- Copy of the legal title reportLEGAL REPORT PART 1.pdf · uploaded 30 Jun 2020Source
- Copy of the legal title reportLEGAL REPORT PART 2.pdf · uploaded 30 Jun 2020Source
- Copy of the legal title report2 LEGAL TITLE REPORT CHALLANS.pdf · uploaded 30 Jun 2020View
- Declaration about Commencement CertificateAffidavite.pdf · uploaded 15 Aug 2021View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Certificate in form 5 Shri Apparment Milan and Raja Prajapati 21149072AAAACQ4746.pdf · uploaded 15 Aug 2021Source
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letter10 PERFOMA AGREEMENT.pdfSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhusawal (CT), Bhusawal taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
CTS NO 200/9,10,11,12,13,30,31,32,33,34
Boundaries
- North
- 12 M Wide Road
- South
- Cts No 200-35
- East
- Cts No 200-6
- West
- Cts No 200-14
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Prashant R Patil | — |
| Chartered accountant | Ca Gopal Agrawal | — |
| Engineer | Prashant R Patil | — |
Source: MahaRERA project page. Contact details are not shown.