Skip to content
Deedo home
Menu
BLD_007961Completed3 floors

Samruddhi Heights Phase II · Samruddhi Heights Phase II

Bhusawal (Ct) · RERA P49900015760

3Sanctioned habitable floorsregistration certificate
30 Apr 2022Revised completionpromised 30 Mar 2021

Floors

3 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P49900015760 · registered 22 Mar 2018
Promised completion
30 Mar 2021
Revised completion
30 Apr 2022
Sanctioned habitable floors
3

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
FLAT NO 0153.9 m² (580 sq.ft)1not published
FLAT NO 0253.6 m² (577 sq.ft)1not published
FLAT NO 0352.6 m² (567 sq.ft)1not published
FLAT NO 0448.3 m² (520 sq.ft)1not published
FLAT NO 0548.5 m² (522 sq.ft)1not published
FLAT NO 0656.6 m² (609 sq.ft)1not published
FLAT NO 0752.6 m² (567 sq.ft)1not published
FLAT NO 0848.3 m² (520 sq.ft)1not published
FLAT NO 0948.5 m² (522 sq.ft)1not published
FLAT NO 1056.6 m² (609 sq.ft)1not published
Total10

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0001
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology