Ramai Keshav Vihar Phase 3
CompletedBhusawal (Ct), Jalgaon 425201 |Promoter: Vishal Rajendra Natkar
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 1
- Unit types
- 2BHK16 units in all
- Land area for this project
- 437 sq m (4,707 sq ft)
- Permissible built-up area
- 524 sq m (5,643 sq ft)
- Sanctioned built-up area
- 524 sq m (5,643 sq ft)
- Address
- Plot No 2 S No 94/2 Cts No 4349/4/2, Plot No 2 S No 94/2 Cts No 4349/4/2/2, SatarePIN 425201
- Designated bank account
- The Jalgaon Peopels Cooperative Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 20 Sep 2021
- Promised
- 31 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P49900030872 | 20 Sep 2021 | 31 Dec 2023 | — | Vishal Rajendra Natkar | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Ramai Keshav Vihar Phase 3 | 4 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
16 units registered
| Type | Carpet area | Units |
|---|---|---|
| 2BHK | 32.76 sq m · 353 sq ft | 16 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 1 |
| Open Space | 0 | 0 | 0 | 0 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Ramai Keshav Vihar Phase 3
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
12 documents held by Deedo, 16 filings listed on MahaRERA's project page
Document library
- Copy of the legal title reportLEGAL SCRUTINY REPORT.pdf · uploaded 3 Sep 2021View
- Details of encumbrancesENCUMBRANCES CERTIFICATE.pdf · uploaded 3 Sep 2021View
- Declaration in FORM BFOR B DECLARATION VIDYA_compressed.pdf · uploaded 3 Sep 2021View
- Building Plan Approval / NA Order for plotted developmentAPPENDIX D-1.pdf · uploaded 3 Sep 2021View
- Proforma of Allotment letterFOR B DECLARATION VIDYA_compressed.pdf · uploaded 3 Sep 2021View
- Copy of Layout Approval (in case of layout)snactioned-plan.pdf · uploaded 15 Sep 2021View
- Declaration about Commencement CertificateFORM-D.pdf · uploaded 15 Sep 2021View
- Commencement Certificates / NA Order for plotted developmentAPPENDIX D-1.pdf · uploaded 15 Sep 2021View
- Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 5 ANNUAL REPORT 1.pdf · uploaded 6 Nov 2023View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION-PHASE-3.pdf · uploaded 6 Nov 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 ANNUAL REPORT 1.pdf · uploaded 29 Dec 2023View
Promoter documents
Proforma allotment letter
- Proforma allotment letterFOR B DECLARATION VIDYA_compressed.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhusawal (CT), Bhusawal taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PLOT NO 2 S NO 94/2 CTS NO 4349/4/2
Boundaries
- North
- Cts 4349 4 3
- South
- Cts 4349 4 1
- East
- Road
- West
- Cts No 4349 3
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rajesh Chandan | — |
| Chartered accountant | Ca Tejas Kasat | — |
| Engineer | Rajesh Chandan | — |
Source: MahaRERA project page. Contact details are not shown.