Skip to content

Gondiya

Deedo IDDL-GON-GONDIYA

5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4in 2 localities
Registrations4
Completion still due02 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases1on 1 project

5 in 10 registrations run late here

4 MahaRERA registrations in Gondiya and the places within it

2 past even the latest date2 no date on record

Projects in Gondiya

4 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Salasar EnclaveSafegain Investments & InfrastructureCompleted——
Ashtavinayak ResidencyMaa Nainadevi Builders & Developres Private Limited2 mo late——
Ashtavinayak HeightsMaa Nainadevi Builders & Developres Private LimitedNo date on record——
Pm1110002500054No date on record——
Gondiya market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Localities in Gondiya

Most active promoters

  1. Maa Nainadevi Builders & Developres Private Limited1 project
  2. Maa Nainadevi Builders & Developres Private Limited1 project
  3. Safegain Investments & Infrastructure1 project

Gondiya, in questions

How many projects in Gondiya run late?

5 in 10 MahaRERA registrations (2 of 4): their completion date was extended or has passed, data through 8 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Gondiya by Deedo. Medians on fewer than 3 deeds are not shown.

Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology