Skip to content

Gadchiroli

Deedo IDDL-GAD-GADCHIROLI

6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects10in 5 localities
Registrations10
Completion still due15 past their date
Median extension4 months17% of registrations extended
Regulatory cases2on 2 projects

6 in 10 registrations run late here

10 MahaRERA registrations in Gadchiroli and the places within it

1 extended, not yet due5 past even the latest date4 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Gadchiroli

10 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Divya Gruha ResidencyMarkhanday Developer and BuildersDue Apr 2029, extended 4 mo——
Residential LayoutRam Builders And DevelopersCompleted——
Residential Layout At Mauza - Amgaon, S. No. - 12Keshao Harishchandra Warjurkar3 yrs 11 mo late——
Markandeya ApartmentRam Builders And DevelopersCompleted—100%
Shree Ganesh ApartmentPrabhakar Akhade5 yrs 11 mo late——
All 10 projects →
Gadchiroli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Localities in Gadchiroli

Most active promoters

  1. Ram Builders And Developers2 projects
  2. Anand Namdeorao Shrungarpawar1 project
  3. Friends Developers1 project
  4. Keshao Harishchandra Warjurkar1 project
  5. Markhanday Developer And Builders1 project
  6. Prabhakar Akhade1 project
  7. Samstithiinfrasructures Private Limited1 project

Gadchiroli, in questions

How many projects in Gadchiroli run late?

6 in 10 MahaRERA registrations (6 of 10): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Gadchiroli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology