BLD_006257Completed42 floors
Chandravel 3 · Chandravel3
Walwadi (Ct) · RERA P49800001074
42Sanctioned habitable floorsregistration certificate
31 Dec 2019Promised completion
Floors
42 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 42
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| BUNGLOW 10 A | 60.2 m² (648 sq.ft) | 1 | not published |
| BUNGLOW 10 B | 58 m² (624 sq.ft) | 1 | not published |
| BUNGLOW 10 C | 60.2 m² (648 sq.ft) | 1 | not published |
| BUNGLOW 11 A | 58.1 m² (625 sq.ft) | 1 | not published |
| BUNGLOW 11 B | 57.6 m² (620 sq.ft) | 1 | not published |
| BUNGLOW 11 C | 58.1 m² (625 sq.ft) | 1 | not published |
| BUNGLOW 12 A | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 12 B | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 13 A | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 13 B | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 14 A | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 14 B | 71 m² (765 sq.ft) | 1 | not published |
| BUNGLOW 15 A | 61.9 m² (666 sq.ft) | 1 | not published |
| BUNGLOW 15 B | 61.9 m² (666 sq.ft) | 1 | not published |
| BUNGLOW 16 A | 61.9 m² (666 sq.ft) | 1 | not published |
| BUNGLOW 16 B | 61.9 m² (666 sq.ft) | 1 | not published |
| BUNGLOW 17 A | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 17 B | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 18 A | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 18 B | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 19 A | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 19 B | 68.2 m² (734 sq.ft) | 1 | not published |
| BUNGLOW 1 A | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 1 B | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 20A | 65.5 m² (705 sq.ft) | 1 | not published |
| BUNGLOW 20 B | 63.4 m² (682 sq.ft) | 1 | not published |
| BUNGLOW 20 C | 65.5 m² (705 sq.ft) | 1 | not published |
| BUNGLOW 2 A | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 2 B | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 3 A | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 3 B | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 4 A | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 4 B | 58.6 m² (631 sq.ft) | 1 | not published |
| BUNGLOW 6 A | 59.4 m² (639 sq.ft) | 1 | not published |
| BUNGLOW 6 B | 56.9 m² (613 sq.ft) | 1 | not published |
| BUNGLOW 6 C | 59.4 m² (639 sq.ft) | 1 | not published |
| BUNGLOW 7 A | 63.8 m² (687 sq.ft) | 1 | not published |
| BUNGLOW 7 B | 63.8 m² (687 sq.ft) | 1 | not published |
| BUNGLOW 8 A | 63.8 m² (687 sq.ft) | 1 | not published |
| BUNGLOW 8 B | 63.8 m² (687 sq.ft) | 1 | not published |
| BUNGLOW 9A | 63.8 m² (687 sq.ft) | 1 | not published |
| BUNGLOW 9 B | 63.8 m² (687 sq.ft) | 1 | not published |
| Total | 42 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)100%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through8 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology