Not yet due2 floorsRERA P49800078617

9, Anandvan

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Promised completion31 Mar 2030RERA registration
Units & parking in 9

MahaRERA's project page with unit types hasn't been imported for this registration.

Parking: Closed/Covered 0 · Open Space 1 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation60%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth25%
  • Stilt Floor0%
  • Slabs of Super Structure20%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
RERA registration
P49800078617 · registered 27 Dec 2024
Promised completion
31 Mar 2030
Sanctioned habitable floors
2
Deedo ID
BLD_006387
Data through9 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology