Yashada Govind City Corporation
Deedo IDDD-A0GPOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sterling BloomsP52100003148 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2022 | 30 Jun 2023 | +12 mo |
| Brand SquareP52100003247 | Pimpale Saudagar | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +47 mo* |
Yashada Govind City Corporation, in questions
Does Yashada Govind City Corporation finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 30 mo late. Across Maharashtra, 73% kept their date.
How many projects has Yashada Govind City Corporation registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Yashada Govind City Corporation have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.