Xrbia Warai Developers Private Limited
Deedo IDDD-B9MWOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 65 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Xrbia Warai / Neral - Ph 2Regulatory order: PROJECT NAME: XRBIA WARAI/NERAL-PH 2 (Regulatory Case No. 41 of 2023) dated 13 September 2023. | 15 Sep 2023 |
| Regulatory order | Xrbia Warai NeralRegulatory order: PROJECT NAME: XRBIA WARAI/NERAL-PH 1 (Regulatory Case No. 40 of 2023) dated 13 September 2023. | 15 Sep 2023 |
| Listed as an NCLT insolvency project | Xrbia Warai NeralListed as NCLT project: Xrbia Warai / Neral - Ph 1 | Not on record |
| Listed as an NCLT insolvency project | Xrbia Warai NeralListed as NCLT project: Xrbia Warai / Neral - Ph 3 | Not on record |
| Listed as an NCLT insolvency project | Xrbia Warai / Neral - Ph 2Listed as NCLT project: Xrbia Warai / Neral - Ph 2 | Not on record |
| Listed as an NCLT insolvency project | Xrbia Thane Ph 3Listed as NCLT project: Xrbia Thane Ph 3 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Xrbia Warai NeralP52000002246 | Varai T Waredi | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
| Xrbia Warai NeralP52000002828 | Varai T Waredi | Certificate Signed | 30 Jun 2021 | 29 Dec 2022 | +65 mo* |
| Xrbia Warai / Neral - Ph 2P52000004499 | Varai T Waredi | Certificate Signed | 30 Jun 2021 | 29 Dec 2022 | +65 mo* |
| Xrbia Thane Ph 3P51700021558 | Sarang | Certificate Signed | 30 Dec 2028 | 30 Dec 2028 | On date |
Xrbia Warai Developers Private Limited, in questions
Does Xrbia Warai Developers Private Limited finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 65 mo late. Across Maharashtra, 73% kept their date.
How many projects has Xrbia Warai Developers Private Limited registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Xrbia Warai Developers Private Limited have MahaRERA regulatory cases?
6 regulatory cases name its registrations, including an insolvency (NCLT) case.