Company or firm · first RERA registration 2017

Wadhwa Buildcon Llp

Deedo IDDD-AMJB

Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.

Projects24 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay47 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases7includes insolvency

4 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Wadhwa RhodesiaP51700002499Bhiwandi (M Corp.)Certificate Signed31 Dec 201931 Dec 2026+84 mo
Wadhwa RhodesiaP51700007370Bhiwandi (M Corp.)Certificate Signed30 Dec 202231 Dec 2027+60 mo
Wadhwa RegaliaP51700010114NetivaliLapsed30 Dec 2025—+10 mo*
Wadhwa RegaliaP51700011989NetivaliCertificate Signed30 Dec 202330 Dec 2023+34 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology