Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Netivali · Thane
Registration
RERA numbers
PromoterWadhwa Buildcon LLP
Status on MahaRERACertificate Signed, Lapsed
Registered on16 Aug 2017
Delivery
Promised completion30 Dec 2025
Revised completion30 Dec 2023
Delay vs RERA date+9 monthslatest date on record has passed
Extension certificates1
Size
Project land area2,317 sq m
Buildings on record6
Units129
Units booked5240% of units
Regulatory
MahaRERA cases5complaint (2)Listed as an NCLT insolvency project (3)
Documents on file37
Last checked on MahaRERA13 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology