Vsk Builders And Developres
Deedo IDDD-K1EPOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 43 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vsk CityP51500021150 | Babhulgaon | Certificate Signed | 20 Apr 2023 | 20 Apr 2023 | +43 mo* |
Vsk Builders And Developres, in questions
Does Vsk Builders And Developres finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 43 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vsk Builders And Developres registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Vsk Builders And Developres have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.