Vithai Developers

Deedo IDDD-3EMK

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 71 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay71 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vithai DevelopersP52100018678CharholiLapsed30 Nov 202029 May 2022+71 mo*

Vithai Developers, in questions

Does Vithai Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 71 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vithai Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Vithai Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.