Vision Developers

Deedo IDDD-0DMZ

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 10 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay10 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
HerambP52700048988ParleCertificate Signed7 Nov 20247 Nov 2024+24 mo*
HerambP52700056170ParleCertificate Signed23 Jan 202623 Jan 2026+10 mo*
Heramb ResidencyPR1300002600282Karad (M Cl)Certificate Signed31 Dec 202830 Apr 2029+4 mo

Vision Developers, in questions

Does Vision Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 10 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vision Developers registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Vision Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology