Vision Ace

Deedo IDDD-4QVD

Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay8 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vision Ace Phase 1P52100017748TathwadeCertificate Signed30 Oct 202330 Oct 2023On date
Vision Ace Phase IIP52100022545TathwadeCertificate Signed30 Oct 202430 Oct 2024On date
Vision Ace Commercial Phase IP52100026126TathwadeCertificate Signed28 Sep 202628 Jan 2027+4 mo
Vision Ace MHADAP52100026135TathwadeCertificate Signed30 Oct 202230 Oct 2023+12 mo

Vision Ace, in questions

Does Vision Ace finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vision Ace registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.

Does Vision Ace have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology