Vision Ace
Deedo IDDD-4QVDOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vision Ace Phase 1P52100017748 | Tathwade | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Vision Ace Phase IIP52100022545 | Tathwade | Certificate Signed | 30 Oct 2024 | 30 Oct 2024 | On date |
| Vision Ace Commercial Phase IP52100026126 | Tathwade | Certificate Signed | 28 Sep 2026 | 28 Jan 2027 | +4 mo |
| Vision Ace MHADAP52100026135 | Tathwade | Certificate Signed | 30 Oct 2022 | 30 Oct 2023 | +12 mo |
Vision Ace, in questions
Does Vision Ace finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vision Ace registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Vision Ace have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.