Vishwa Developers And Infrastructures
Deedo IDDD-5MTKOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vishwa NathP52000024321 | Dongari | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
Vishwa Developers And Infrastructures, in questions
Does Vishwa Developers And Infrastructures finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vishwa Developers And Infrastructures registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Vishwa Developers And Infrastructures have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.