Vishal Rajendra Natkar
Deedo IDDD-M9DAOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 45 mo late.
Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay45 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ramai Keshav Vihar Phase-1P49900024375 | Bhusawal (Ct) | Lapsed | 1 Jan 2023 | — | +45 mo* |
| Ramai Keshav Vihar Phase-2P49900027325 | Bhusawal (Ct) | Completed | 30 Mar 2023 | — | On date |
| Ramai Keshav Vihar Phase 3P49900030872 | Bhusawal (Ct) | Completed | 31 Dec 2023 | — | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology