Viraj Properties
Deedo IDDD-YP3SOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| 40 Hyde ParkP52100003914 | Pune (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| AnandwanP52100026004 | Ambegaon Bk | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Bird Nest Cooperative Housing Society LimitedP52100055025 | Ghorpadi | Certificate Signed | 31 Jan 2028 | 31 May 2028 | +4 mo |
Viraj Properties, in questions
Does Viraj Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Viraj Properties registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Viraj Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.