Company or firm · first RERA registration 2022
Viraj Infra Heights
Deedo IDDD-4H3TOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 15 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay15 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Ganraj HeightsDeregistered: Ganraj Heights | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ganraj HeightsP50500047070 | Nagpur (M Corp.) | Certificate Signed | 31 Aug 2025 | 31 Aug 2025 | +15 mo* |
Viraj Infra Heights, in questions
Does Viraj Infra Heights finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.
How many projects has Viraj Infra Heights registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Viraj Infra Heights have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology