Vinod Ramashry Tripathi

Deedo IDDD-5VX8

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay22 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Maple EnclaveP50500013298HingnaCertificate Signed31 Dec 201830 Oct 2020+22 mo

Vinod Ramashry Tripathi, in questions

Does Vinod Ramashry Tripathi finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vinod Ramashry Tripathi registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Vinod Ramashry Tripathi have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology