Vinayaka Realtors And Developers
Deedo IDDD-9Q6MOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 24 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Solomon ResidencyP51800010650 | Kurla | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Nandadeep ResidencyP51800015173 | Kurla | Certificate Signed | 28 Nov 2022 | 27 Nov 2023 | +48 mo* |
| Rose GardenP51800022587 | Marol | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Simra ResidencyP51800029958 | Kurla | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
Vinayaka Realtors And Developers, in questions
Does Vinayaka Realtors And Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vinayaka Realtors And Developers registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Vinayaka Realtors And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.