Company or firm · first RERA registration 2017

Vinayaka Realtors And Developers

Deedo IDDD-9Q6M

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 24 mo late.

Projects44 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay24 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Solomon ResidencyP51800010650KurlaCertificate Signed31 Dec 201930 Dec 2021+24 mo
Nandadeep ResidencyP51800015173KurlaCertificate Signed28 Nov 202227 Nov 2023+48 mo*
Rose GardenP51800022587MarolCertificate Signed31 Mar 202631 Mar 2026On date
Simra ResidencyP51800029958KurlaCertificate Signed31 Dec 202431 Dec 2024+23 mo*

Vinayaka Realtors And Developers, in questions

Does Vinayaka Realtors And Developers finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vinayaka Realtors And Developers registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Vinayaka Realtors And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology