Vinayak Developers
Deedo IDDD-RGKZOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 65 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Samruddhi HeightsP52100005316 | Chikhali Bk. | Certificate Signed | 31 Jan 2019 | 31 Jul 2022 | +94 mo* |
| Samrudhhi HeritageP52100032607 | Chikhali | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +35 mo* |
Vinayak Developers, in questions
Does Vinayak Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 65 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vinayak Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Vinayak Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
