Vinayak Developers

Deedo IDDD-RGKZ

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 65 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay65 mowhen late
First sales on record11registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Samruddhi HeightsP52100005316Chikhali Bk.Certificate Signed31 Jan 201931 Jul 2022+94 mo*
Samrudhhi HeritageP52100032607ChikhaliCertificate Signed31 Dec 202331 Dec 2023+35 mo*

Vinayak Developers, in questions

Does Vinayak Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 65 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vinayak Developers registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Vinayak Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology