Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay11 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Orovia Phase 1P51700005653Thane (M Corp.)Certificate Signed30 Mar 202330 Mar 2023On date
Vijay Vatika -5P51700005805Thane (M Corp.)Certificate Signed30 Sep 201830 Sep 2019+12 mo
Orion -3P51700006838Thane (M Corp.)Certificate Signed30 Dec 202030 Oct 2021+10 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology