Vicky Kashinath Bhoir

Deedo IDDD-M76P

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 41 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay41 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mangalmurti ResidencyP52000028029PanvelCertificate Signed30 Jun 202330 Jun 2023+41 mo*

Vicky Kashinath Bhoir, in questions

Does Vicky Kashinath Bhoir finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 41 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vicky Kashinath Bhoir registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Vicky Kashinath Bhoir have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology