Company or firm · first RERA registration 2019

Vibha Realtors

Deedo IDDD-2M00

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 66 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay66 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The One PearlP51700021190KalyanCertificate Signed28 May 202131 May 2024+66 mo*

Vibha Realtors, in questions

Does Vibha Realtors finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 66 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vibha Realtors registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Vibha Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology