Company or firm · first RERA registration 2017
Venturespro Projects LLP
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 6 mo — longer than Maharashtra's 4 mo.
Projects23 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay6 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| EterniaP52100003139 | Hadapsar | Certificate Signed | 30 May 2020 | 30 Nov 2020 | +6 mo |
| EterniaP52100021956 | Hadapsar | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Profitbay - Bt Kawade RoadP52100033914 | Ghorpadi | Certificate Signed | 31 Aug 2026 | 31 Aug 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology