Venkatesh Associates
Deedo IDDD-3M19Of 8 registrations whose promised date has arrived, 6 kept it (75%). The rest ran a median 17 mo late.
Delivery record
4 of 12 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 12 registrations
12 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Venkatesh GalaxyP52100006088 | Kondhwa Bk | Certificate Signed | 1 Jul 2019 | 1 Jul 2019 | On date |
| Venketesh Galaxy Wing D1P52100021669 | Kondhwa Bk | Certificate Signed | 15 Jul 2022 | 15 Jul 2022 | On date |
| Venkatesh Galaxy Wing D2 and FP52100033881 | Kondhwa Bk | Certificate Signed | 31 Oct 2022 | 31 Oct 2022 | On date |
| Venkatesh Hill Side, Plot No. 2, Building 1P52100045700 | Dhayari | Certificate Signed | 31 May 2024 | 30 Nov 2025 | +30 mo* |
| Venkatesh HillsideP52100045766 | Dhayari (Part) | Certificate Signed | 31 May 2024 | 31 May 2024 | On date |
| Crystal Paradise Building A, BP52100045774 | Kondhwa Bk | Certificate Signed | 31 May 2024 | 31 May 2024 | +30 mo* |
| LAKE TOWN D-6, WING - A and BP52100053248 | Katraj | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Venkatesh HillsideP52100077270 | Dhayari (Part) | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| Venkatesh KamalaPR1260002502850 | Sadashiv Peth | Certificate Signed | 17 Dec 2028 | 17 Apr 2029 | +4 mo |
| Venkatesh HillsidePR1260002601043 | Dhayari | Certificate Signed | 31 Oct 2028 | 28 Feb 2029 | +4 mo |
| Venkatesh HillsidePR1260002601434 | Dhayari | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Venkatesh GitanjaliPR1260002601871 | Sadashiv Peth | Certificate Signed | 31 Oct 2028 | 31 Oct 2028 | On date |
Show all 12 registrationsShow fewer
Venkatesh Associates, in questions
Does Venkatesh Associates finish projects on time?
Of 8 MahaRERA registrations whose promised completion date has arrived, 6 kept it (75%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Venkatesh Associates registered with MahaRERA?
10 projects under 12 MahaRERA registrations; 6 completed on MahaRERA.
Does Venkatesh Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.