Vedbhumi Builders & Developers Pvt. Ltd
Deedo IDDD-PMBFOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 71 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VatsalyabhumiP50500013281 | Nagpur (M Corp.) | Certificate Signed | 30 Oct 2019 | 31 Dec 2025 | +85 mo* |
| BarsanaP50500013341 | Nagpur (M Corp.) | Certificate Signed | 31 Jul 2018 | 30 Jun 2024 | +71 mo |
| BrijP50500013364 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Vedbhumi Builders & Developers Pvt. Ltd, in questions
Does Vedbhumi Builders & Developers Pvt. Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 71 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vedbhumi Builders & Developers Pvt. Ltd registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Vedbhumi Builders & Developers Pvt. Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.