Company or firm · first RERA registration 2021

Vedant Spaces

Deedo IDDD-0AQF

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Arv UthvilleP52100030680KharadiCertificate Signed31 Dec 202430 Dec 2025+12 mo

Vedant Spaces, in questions

Does Vedant Spaces finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vedant Spaces registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Vedant Spaces have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology