Vastukrupa Construction (India) Pvt Ltd
Deedo IDDD-BHFBOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Business SquareP51600000211 | Nashik | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Business SquareP51600014004 | Nashik | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
Vastukrupa Construction (India) Pvt Ltd, in questions
Does Vastukrupa Construction (India) Pvt Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 31 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vastukrupa Construction (India) Pvt Ltd registered with MahaRERA?
1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Vastukrupa Construction (India) Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.