Vastu Infra

Deedo IDDD-E3NT

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay22 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Satyam Co-Op Housing Society LtdP52000013577KalamboliCertificate Signed20 Aug 202320 Aug 2023+39 mo*
Ridhima CHS LTDPM1270002502309KalamboliCertificate Signed30 Oct 202828 Feb 2029+4 mo

Vastu Infra, in questions

Does Vastu Infra finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vastu Infra registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Vastu Infra have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology