Varun Homes Pvt Ltd
Deedo IDDD-ACSKOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Safal Sky Redevelopment Of Ameya Chs LtdP51800004137 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Safal Ganga SmrutiP51800024417 | Kurla | Certificate Signed | 30 Nov 2026 | 30 Nov 2026 | On date |
Varun Homes Pvt Ltd, in questions
Does Varun Homes Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Varun Homes Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Varun Homes Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.