Varada Dream Homes
Deedo IDDD-72X4Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late.
Delivery record
3 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| GanadheeshP52100034512 | Baner | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| MorayaP52100047661 | Baner | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| VinayakP52100054303 | Baner | Certificate Signed | 30 Apr 2025 | 30 Apr 2025 | +19 mo* |
| HerambPR1260002500395 | Baner | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| SudattaPR1260002502909 | Baner | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| VishnuPR1260002503084 | Baner | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Varada Dream Homes, in questions
Does Varada Dream Homes finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Varada Dream Homes registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 3 completed on MahaRERA.
Does Varada Dream Homes have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.