Skip to content
Company or firm · first RERA registration 2022

Varad Associates

Deedo IDDD-RF7D

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Varad ResidencyP51600046873Deolali (Cb)Certificate Signed31 Mar 202731 Jul 2027+4 mo
Varad HeightsP51600080577DeolaligaonCertificate Signed31 Mar 202931 Jul 2029+4 mo

Varad Associates, in questions

Does Varad Associates finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Varad Associates registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Varad Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology