Company or firm · first RERA registration 2017

Vaishnavi Promoters And Developers

Deedo IDDD-NP43

Of 5 registrations whose promised date has arrived, 1 kept it (20%). The rest ran a median 18 mo late.

Projects99 RERA registrations
Kept RERA date20%Maharashtra: 73%
Median delay18 mowhen late
First sales on record17registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

7 of 9 registrations with dates moved or missed their RERA date · months late against the original promise

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vaishnavi VastuP52100004671NarayangaonCertificate Signed30 Jun 202330 Jun 2023+41 mo*
Sahil Vighnesh ResidencyP52100005542WakadCertificate Signed31 Dec 201930 Dec 2021+24 mo
Sahil HeightsP52100010663Pimpri Chinchawad (M Corp.)Certificate Signed30 Jun 201930 Jun 2019On date
Sahil Om ParkP52100011417MoshiCertificate Signed30 Jun 202130 Dec 2022+18 mo
Shubh ShagunP52100026994ChovisawadiCertificate Signed31 Dec 202731 Dec 2027On date
Trinity PlazaP52100050446MoshiCertificate Signed1 Feb 202531 Dec 2026+22 mo
Vaishnavi Homes A WingP52100054677MarunjiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Sahil Heights A1P52100054948Pimple NilakhCertificate Signed31 Dec 202730 Apr 2028+4 mo
Vaishnavi Vastu A and BP52100056342VarulwadiCertificate Signed31 Dec 202730 Apr 2028+4 mo

Vaishnavi Promoters And Developers, in questions

Does Vaishnavi Promoters And Developers finish projects on time?

Of 5 MahaRERA registrations whose promised completion date has arrived, 1 kept it (20%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Vaishnavi Promoters And Developers registered with MahaRERA?

9 projects under 9 MahaRERA registrations; 3 completed on MahaRERA.

Does Vaishnavi Promoters And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology