Company or firm · first RERA registration 2024

Vaidya Spaces Private Limited

Deedo IDDD-EHSX

None of 3 registrations has reached its promised completion date yet.

Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vaidya West World - HarmonyP51800055721GundavaliCertificate Signed31 Jul 202731 Jul 2027On date
Vaidya West World - SerenityP51800055855GundavaliCertificate Signed31 Aug 202731 Dec 2027+4 mo
Vaidya West World -One AeropolisP51800077018GundavaliCertificate Signed3 Jun 20283 Oct 2028+4 mo

Vaidya Spaces Private Limited, in questions

Does Vaidya Spaces Private Limited finish projects on time?

None of its 3 MahaRERA registrations has reached its promised completion date yet.

How many projects has Vaidya Spaces Private Limited registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Vaidya Spaces Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology