Vaibhav Shashikant Kadam
Deedo IDDD-JZM7Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 9 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hira Chambers CHSP51700034036 | Thane (M Corp.) | Certificate Signed | 31 Oct 2025 | 31 Oct 2025 | +13 mo* |
| Surshree Co Op Hsg Soc LtdP51700079917 | Naupada | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Vaibhav Shashikant Kadam, in questions
Does Vaibhav Shashikant Kadam finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 9 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vaibhav Shashikant Kadam registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Vaibhav Shashikant Kadam have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.