Skip to content
Company or firm · first RERA registration 2021

Urban Spacess Veraco Realtors

Deedo IDDD-S625

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 35 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay35 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vision PlusP52100029565Pimpri Chinchawad (M Corp.)Certificate Signed31 Dec 202331 Dec 2023+35 mo*

Urban Spacess Veraco Realtors, in questions

Does Urban Spacess Veraco Realtors finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.

How many projects has Urban Spacess Veraco Realtors registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Urban Spacess Veraco Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology