United Builders

Company or firm · 4 projects · 4 MahaRERA registrations · 1 reported completed

Projects44 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
United Shalimar Phase 2P51600001027Nashik (M Corp.)2017Lapsed31 Dec 201830 Dec 2024+72 months
United Sanskruti Phase IP51600001099Nashik2017Completed31 Mar 2018—On date
United Courtyard Phase IP51600001925Nashik2017Not reported31 Mar 201930 Sep 2020+18 months
United Courtyard Phase 2P51600026084Nashik2020Not reported30 Sep 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • United Shalimar Phase 2+72 mo
  • United Sanskruti Phase IOn date
  • United Courtyard Phase I+18 mo
  • United Courtyard Phase 2On date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 72 months, for United Shalimar Phase 2 (P51600001027).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology