United Builders
Deedo IDDD-AJ9WOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 57 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| United Shalimar Phase 2P51600001027 | Nashik (M Corp.) | Lapsed | 31 Dec 2018 | 30 Dec 2024 | +95 mo* |
| United Sanskruti Phase IP51600001099 | Nashik | Completed | 31 Mar 2018 | — | On date |
| United Courtyard Phase IP51600001925 | Nashik | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| United Courtyard Phase 2P51600026084 | Nashik | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
United Builders, in questions
Does United Builders finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 57 mo late. Across Maharashtra, 73% kept their date.
How many projects has United Builders registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does United Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.