Unique Spaces Llp
Deedo IDDD-RYY2None of 4 registrations has reached its promised completion date yet.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| K ShireP52100046102 | Punawale | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| Flow PunawaleP52100047306 | Punawale | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| K ShireP52100050966 | Punawale | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| K ShireP52100078900 | Punawale | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Unique Spaces Llp, in questions
Does Unique Spaces Llp finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Unique Spaces Llp registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Unique Spaces Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.