Unique Group
Deedo IDDD-NQRMOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Unique EliteP52100052416 | Chinchwad | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Unique InfinityP52100078334 | Chinchwad | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Unique VrundavanP52100081000 | Chinchwad | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Unique Group, in questions
Does Unique Group finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Unique Group registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Unique Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.