Company or firm · first RERA registration 2018

Unique Group Unit No.1

Deedo IDDD-065T

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay15 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Unique LifestyleP52100017040WagholiCertificate Signed30 Jun 202129 Dec 2022+18 mo
Agarwal Business HubP52100017079WagholiCertificate Signed30 Dec 202230 Nov 2023+11 mo

Unique Group Unit No.1, in questions

Does Unique Group Unit No.1 finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.

How many projects has Unique Group Unit No.1 registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Unique Group Unit No.1 have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology