Company or firm · first RERA registration 2022

Unique Choice Associates Llp

Deedo IDDD-XGJP

None of 3 registrations has reached its promised completion date yet.

Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Que 914 Phase IP52100046034KeshavnagarmundwaCertificate Signed31 Dec 202631 Dec 2026On date
Que 914 Phase IIP52100051858MundhawaCertificate Signed30 Jun 202730 Jun 2027On date
Que 914 Phase IIIP52100078292MundhawaCertificate Signed31 Mar 202831 Jul 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology