Que 914 Phase I
Certificate SignedKeshavnagarmundwa, Pune 411036 |Promoter: Unique Choice Associates LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 1BHK, 2BHK, 3BHK, 4BHK257 units in all
- Address
- 9-14/1/33, 9-14/1/34, Keshavnagar, Mundhwa, 24 mtr DP Road, Keshavnagar, MundhwaPIN 411036
- Designated bank account
- 109
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2026
- Registered
- 15 Jun 2022
- Promised
- 31 Dec 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100046034 | 15 Jun 2022 | 31 Dec 2026 | 31 Dec 2026 | Unique Choice Associates LLP | Project page |
2 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
251 of 257 units booked (98%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A | 1BHK | 35.11 sq m · 378 sq ft | 1 | 1 |
| A | 2BHK | 46.57 sq m · 501 sq ft | 43 | 43 |
| B | 2BHK | 70.03 sq m · 754 sq ft | 41 | 41 |
| B | 3BHK | 79.82 sq m · 859 sq ft | 42 | 41 |
| B | 3BHK | 89.33 sq m · 962 sq ft | 88 | 83 |
| B | 4BHK | 100.11 sq m · 1,078 sq ft | 42 | 42 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 111 filings listed on MahaRERA's project page
Finance
- PAN CardUnique Choice Associates LLP Pancard.pdf · uploaded 30 May 2022Source
Legal
Show all 112 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesNo Encumbrance Letter.pdf · uploaded 30 May 2022Source
- 2 Details of encumbrancesNo Security Undertaking.pdf · uploaded 30 May 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout Sanction.pdf · uploaded 30 May 2022Source
- 2 Copy of Layout Approval (in case of layout)Layout Commencement.pdf · uploaded 30 May 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Sanction.pdf · uploaded 30 May 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Commencement Certificate.pdf · uploaded 30 May 2022Source
- 1 Declaration about Commencement CertificateFormat D CC Declaration.pdf · uploaded 30 May 2022Source
- 1 Declaration in FORM BForm B.pdf · uploaded 30 May 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 30 May 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 30 May 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate.pdf · uploaded 30 May 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200236861307_For_Debtor_Based_Search_07_05_2022_18_26_26_378.pdf · uploaded 30 May 2022Source
- 2 CERSAI detailsCERSAI_Search_Report_200236861721_For_Asset_Based_Search_07_05_2022_18_32_23_426.pdf · uploaded 30 May 2022Source
- 1 Disclosure of sold/ booked inventorySold Unsold List.pdf · uploaded 30 May 2022Source
- 1 Proforma of Allotment letterAPPLICATION FORM.pdf · uploaded 30 May 2022Source
- 2 Proforma of Allotment letterProforma of Allotment Letter.pdf · uploaded 30 May 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 31 May 2022Source
- 3 Proforma of Allotment letterFinal Agreement to sale draft (1).pdf · uploaded 31 May 2022Source
- 4 Proforma of Allotment letterFinal Agreement Draft A_Mhada_Building.pdf · uploaded 3 Sep 2022Source
- 5 Proforma of Allotment letterFinal Agreement Draft B Building.pdf · uploaded 3 Sep 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 Apr 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Apr 2023Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 1 May 2023Source
- 3 Copy of Layout Approval (in case of layout)Layout - 1.pdf · uploaded 22 Jun 2023Source
- 4 Copy of Layout Approval (in case of layout)Layout - 2.pdf · uploaded 22 Jun 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 22 Jun 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 22 Jun 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 22 Jun 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 22 Jun 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 22 Jun 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 22 Jun 2023Source
- 8 Building Plan Approval / NA Order for plotted developmentPlan 7.pdf · uploaded 22 Jun 2023Source
- 9 Building Plan Approval / NA Order for plotted developmentPlan 8.pdf · uploaded 22 Jun 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate - 1.pdf · uploaded 22 Jun 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate - 2.pdf · uploaded 22 Jun 2023Source
- 2 Declaration about Commencement CertificateFormat D.pdf · uploaded 22 Jun 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Jul 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Jul 2023Source
- 3 Disclosure of sold/ booked inventoryDisclosure of Inventory 15-07-2023.pdf · uploaded 21 Jul 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 16 Sep 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Oct 2023Source
- 4 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 25 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Oct 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Jan 2024Source
- 5 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 19 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Apr 2024Source
- 6 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 18 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 18 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 Jul 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Jul 2024Source
- 7 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 20 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 (2023-24).pdf · uploaded 21 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 28 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure Of Inventory.pdf · uploaded 6 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 22 Dec 2025Source
- Form 5 (FY 2022-2023)Form 5 (2022-23).pdf · uploaded 22 Dec 2025Source
- Form 5 (FY 2023-2024)Form 5 (2023-24).pdf · uploaded 22 Dec 2025Source
- Form 5 (FY 2024-2025)Form 5 (2024-25).pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 18 Jan 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 18 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 18 Jan 2026Source
- Occupational CertificateCompletion Certificate.pdf · uploaded 14 Mar 2026Source
Technical
- DocumentLayout Sanction.pdf · uploaded 30 May 2022Source
- DocumentLayout Commencement.pdf · uploaded 30 May 2022Source
- DocumentBuilding Sanction.pdf · uploaded 30 May 2022Source
- DocumentLayout - 1.pdf · uploaded 22 Jun 2023Source
- DocumentLayout - 2.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 1.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 2.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 3.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 4.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 5.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 6.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 7.pdf · uploaded 22 Jun 2023Source
- DocumentPlan 8.pdf · uploaded 22 Jun 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Keshavnagar-Mundwa, Pune City taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 9-14-1-29
- South
- 24 mtr DP Road
- East
- S No 9-14-1-35
- West
- S No 9-14-1-32
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Anish Damodar Tambe | — |
| Chartered accountant | Harsh Julaniya | — |
| Engineer | Prashant Tike | — |
Source: MahaRERA project page. Contact details are not shown.