Company or firm · first RERA registration 2022
Unique Associates
Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.
Projects24 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Unique Youtopia Phase IP52100032483 | Kharadi | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
| Unique YoutopiaP52100046003 | Kharadi | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Unique YoutopiaP52100047371 | Kharadi | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| Unique YoutopiaP52100080485 | Kharadi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology